2,000kVA Transformer Package Installation,UK – Undisclosed

  • Where: UK – Undisclosed
  • What: Installation of a 2,000kVA transformer package, GRP enclosure and concrete base blocks.
  • Client: Undisclosed
  • Partner: Non partnered project

The challenge

Unsuitable ground at the front of the site required a stable crane-mat platform before the HIAB lorry loader could be positioned for the lift.

The 2,000kVA transformer, GRP enclosure and heavy concrete base blocks had to be lifted from the access road at significant radius. Ground conditions at the front of the site were unsuitable for direct lorry positioning, so crane mats were used to establish a stable working platform before the vehicle was set up.

Once the platform was in place, the base blocks, transformer package and GRP enclosure were lifted and installed in the required sequence.

Equipment Used

-Lorry loader (HIAB)
-Crane mats
-Specialist lifting slings and shackles

Expertise Provided

-Large transformer package unit installation
-Ground condition assessment and crane mat platform preparation
-Correct installation sequencing for multi-component substation builds
-HIAB lorry loader operations at extended radius
-GRP enclosure rigging and handling

The Result

The concrete base blocks, 2,000kVA transformer package and GRP enclosure were all successfully installed in sequence. The crane-mat platform gave the lorry loader a stable working surface and allowed the lift to proceed despite the ground conditions at the front of the site.

Ground bearing capacity was assessed as part of the pre-job survey, identifying the set-up requirement before the vehicle arrived on site.